Florida Milestone Inspection Deadlines for Pinellas County Condos (2026 Update)

If your board has a certified letter from the building department, or your building is getting close to 30, the first question is simple: when is our inspection due? The answer has shifted since the original law passed in 2022, and a lot of what's still floating around online is out of date. Here is where the rules stand in late 2026 for condos in St. Petersburg, the Gulf beaches, and the rest of Pinellas County.
This is a plain-language summary, not legal advice. Your association attorney and your building department have the final word on your building.
Which buildings need a milestone inspection
Florida's milestone inspection law (section 553.899, Florida Statutes) applies to buildings that are three habitable stories or more, as measured under the Florida Building Code, and that are owned in whole or in part as a condominium or cooperative.
Two details trip boards up:
"Habitable" stories. A 2025 change replaced "three stories" with "three habitable stories." A parking level under two floors of units may not count the way you'd expect. Ask your engineer how the code applies to your building.
Small buildings are exempt. The law does not apply to single-family homes, duplexes, triplexes or fourplexes with three or fewer habitable stories above ground.
When your inspection is due
The statewide rule is:
First inspection: by December 31 of the year the building turns 30, counted from the date the certificate of occupancy was issued.
After that: every 10 years.
What happened to the 25-year coastal rule?
When the law first passed in 2022, buildings within three miles of the coast had to be inspected at 25 years. That automatic coastal rule is gone. The law now says 30 years statewide, but your local building department can require the first inspection at 25 years if local conditions justify it, and the statute names proximity to salt water as an example.
For Pinellas County, that local option matters. Much of the county sits within a few miles of the Gulf or Tampa Bay. So "30 years" is the default, not a guarantee.
Who your building department is
Pinellas County is not one jurisdiction for this. Which office sends your notice and receives your reports depends on where the building is:
Pinellas County Building and Development Review Services handles unincorporated Pinellas plus seven municipalities: Belleair Beach, Belleair Bluffs, Belleair Shore, Indian Rocks Beach, Oldsmar, Safety Harbor and Kenneth City. Its milestone page currently lists the 30-year schedule. Reports are submitted through the Pinellas County Access Portal, and questions go to Milestone@pinellas.gov.
Cities with their own building departments, including St. Petersburg, Clearwater, St. Pete Beach, Treasure Island, Madeira Beach and Indian Shores, run their own milestone programs. Check that city's building department page or call it to confirm whether it uses 30 years or has adopted an earlier trigger.
If you manage buildings in more than one city, don't assume the rules match.
Buildings that were already past 30
Buildings that hit 30 before July 1, 2022 had to complete their first inspection before December 31, 2024. Buildings that turned 30 between July 1, 2022 and December 31, 2024 had until December 31, 2025. If your building falls in either group and you have not filed, talk to your building department and attorney now.
The timeline once the notice arrives
Your building department sends a written notice by certified mail. From there, the clock runs like this:
Step | Deadline |
|---|---|
Board notifies unit owners of the required inspection and its due date | Within 14 days of receiving the notice |
Phase 1 inspection completed | Within 180 days of receiving the notice |
Engineer's Phase 2 progress report, with a completion timeline (only if Phase 1 finds substantial structural deterioration) | Within 180 days of submitting the Phase 1 report |
Inspector's summary sent to every unit owner and posted on the property | Within 45 days of receiving the report, whatever it says |
Repairs commenced | Within 365 days of the building department receiving the Phase 2 report |
If you've hired an engineer or architect and the inspection still can't reasonably be finished in time, the building department can grant an extension for good cause. Ask early. An extension request with a signed engineering contract attached is much stronger than one sent the week before the deadline.
Phase 1 vs. Phase 2
Phase 1 is a visual inspection of the building's primary structural systems by a Florida-licensed engineer or architect. Many buildings stop here: the engineer finds no substantial structural deterioration, files the report and the building is done for 10 years.
Phase 2 is required only when Phase 1 finds substantial structural deterioration. It goes deeper and may include testing that opens up concrete. It ends with a repair program and a timeline. That's when the 365-day repair clock becomes the board's main concern. We covered what to do next in Phase 2 Found Substantial Structural Deterioration. Now What?
What usually drives Phase 2 on Gulf-front and bayfront buildings here:
Concrete spalling on balcony edges, slab soffits and columns
Corroded reinforcing steel from salt exposure
Post-tension cable distress in buildings from the 1970s to 1990s
Failed sealants and waterproofing letting water reach the structure
See how we handle these on our concrete repairs and waterproofing and sealant replacement pages.
How milestone inspections relate to your reserve study
The milestone inspection and the Structural Integrity Reserve Study (SIRS) are separate requirements, but they feed each other. The milestone inspection tells you what is wrong with the structure now. The SIRS plans how the association funds the repair and replacement of major building components over time. If Phase 2 calls for major concrete work, expect it to affect your reserve numbers and possibly a special assessment. Get your reserve study provider and your contractor looking at the same scope early.
Flood zones: watch the 49% rule
If your building is in a flood zone, large repair projects can trigger federal flood rules. Pinellas County notes that repairs cannot exceed 49% of the building's market value unless the whole structure is brought into full compliance with current flood regulations. That can change how you phase a big restoration. Raise it with your engineer and building department before the scope is final.
A planning checklist for boards
Find your certificate of occupancy date. Your building department or the original permit file will have it.
Confirm your building department and its trigger age. Is it 30 years, or has your city adopted 25?
Count your habitable stories with your engineer.
Line up an engineer before the notice arrives. Demand for milestone engineers spikes near each December 31.
Set up owner communication. You have 14 days to notify owners after the notice, and 45 days to distribute the summary after the report.
Get a contractor's eyes on the building early. A pre-inspection walk-through helps you budget before Phase 1 findings arrive.
Align the SIRS and repair plans so the money and the work schedule match.
Frequently asked questions
Is my Pinellas condo inspected at 25 or 30 years?
State law sets 30 years, but your local building department can require 25 years based on local conditions such as closeness to salt water. Unincorporated Pinellas currently lists 30 years. If your building is in a city with its own building department, confirm with that city.
Who pays for the milestone inspection?
The association arranges and pays for the inspection of the portions of the building it is responsible for.
Who can perform the inspection?
A Florida-licensed architect or engineer. A contractor can document conditions and carry out repairs but cannot sign the milestone report.
How long does Phase 1 take?
The law gives you 180 days from the notice to complete it. On-site time is usually days, not weeks, but scheduling the engineer is often the bottleneck.
What happens if Phase 1 finds problems?
A Phase 2 inspection follows. Repairs must start within 365 days of the building department receiving the Phase 2 report.
Do owners get to see the report?
Yes. The association must send owners the inspector's summary within 45 days and post it on the property. Owners can also inspect and copy the full report as an official record.
Can we get an extension?
The building department can extend the initial deadline for good cause, typically when you've already contracted with an engineer and the work can't reasonably be finished in time.
Does my building need both a milestone inspection and a SIRS?
Many do. They are separate requirements. The inspection assesses current structural condition; the SIRS plans long-term funding.
Get ahead of your deadline
Barrett Construction and Restoration works with condo boards and property managers across Pinellas County, from Sand Key and Clearwater Beach to St. Pete Beach and Downtown St. Petersburg. We document conditions for your engineer, price the repair program and carry out the work that follows a milestone inspection.
If your building is approaching 30, has a notice in hand, or has a Phase 2 report on the table, schedule a free walk-through or call (727) 522-6356.